Day 2 Flying Pig

IMG_1537Second day of the 2018 season and first arrival is 43106, fondly nicknamed ‘The Flying Pig’ https://www.svrwiki.com/LMS_Ivatt_Class_4_43106

IMG_1539

IMG_1550

 

Advertisements

2018 season opens

So the first day of running for the 2018 season has arrived. A nice bit of sunshine and perhaps the first dry Saturday this year? Fingers crossed.IMG_1534

Doing the honours on 7802 ‘Bradley Manor’ were Will Marsh and Gary Williams.

Today marks the start of the new timetable A, formulated following a lot of feedback and analysis of the bad and good parts of previous years.

2018 table A plan your day

It has been created in the hope of eliminating avoidable delays and enabling safety-critical staff to have proper rest breaks. It will take a while to get used to, but hopefully it will prove itself in time and will be an enjoyable schedule to operate.

 

 

2017 passenger numbers

The General Manager has issued a notice about passenger numbers for 2017

Total Passengers – which includes, fare paying passengers (pre-book and on the day), Annual Pass Holders, Shareholders and Working Members were 240,686 in 2017 compared with 252,300 the previous year.

We were expecting a lower passenger number in 2017 because we had the ‘one off’ special event Pacific Power in autumn 2016 which attracted 14,000 passengers.

The 2017 Autumn Gala attracted 5,357 passengers in 2017 some 8,643 below Pacific Power.

The weather played a part with snowfall causing the cancellation of 4,000 passenger visits on Sunday 10th December (Santa Specials).

Our usual timetabled passenger numbers from October through the December Festive season were also affected by the weather and in total were 1,893 lower than budget.

If these negative variances are added back in to the 2017 numbers we would have finished ahead of 2016.

County Boundary re-ballast

At County Boundary, the last part of the work is being carried out so that the line can be returned to line speed at that location.

26906939_2014871912129701_9157857430935460072_n

27066980_2014871822129710_7917173696590628253_n

This involves the removal of 70 meters of track and the excavation of the ground below the normal ballast level.

26994354_2014871635463062_7070615644082841952_n

26991649_2014871935463032_1392426652555527765_n

This is composed mostly of ash and the resultant spoil is being shifted to location at the former Kinlet Colliery sidings.

26231829_2014871968796362_4924685579461743589_n

26907770_2014872158796343_6975853180818489215_n

27072728_2015156222101270_7826597082326305412_n

The lower part of the excavation has a plastic “geomesh” laid and imported fresh stone material deposited to a depth of 300mm.

27332492_2014872022129690_8914161385003418758_n

27072617_2015156318767927_6627834849067946583_n

This is overlaid with another layer of geomesh followed by ballast to a depth of 450mm.

27331980_2015156258767933_2847998147497213288_n

26992416_2014872112129681_8768731471313666267_n

The track is then re-laid, ballasted and finally tamped. This work (recommended by the SVR’s consulting engineer) will ensure that we do not suffer future settlement problems as a result of the slip and subsequent remedial works. It has of course resulted in diversion of resources from some of our other planned relaying work but will hopefully negate further visits to the site to repack. (pics by Leigh King, PW Dept staff)

winter works, smaller projects

We’re in the middle of the engineering-works six-week closure when projects can be tackled that require no trains to be running.

Infrastructure Manager Chris Bond reports that this winter sees several smaller projects taking place at various locations rather than the large track relay we saw in 2017 at Waterworks.

48d421_7ae3ed0e06d4425595f691d24d83859c~mv2

 A 500m section of bullhead track from Bewdley Tunnel to the Stourport Road bridge is being cleaned of badly contaminated ballast using a special shaped excavator bucket. The spoil is being removed to an area of the former sugar beet sidings for disposal. The length of track will then be re-ballasted and tamped. It is also intended to weld together the rails to create a length of bullhead CWR which will require the insertion of a pair of breather or expansion switches at the Stourport Road bridge end. At some point in early 2018 we hope to get a Colas rail grinding train to re-profile the railhead to remove the corrugations that cause poor riding.

48d421_2891ac70c5c7433e84c7bcb5a72f0b94~mv2

On the Bewdley side of the tunnel, contractors are using a mini-digger to remove the ballast shoulders using a riddle bucket to remove contamination. The clean ballast is then being placed in between the rails in preparation for fresh ballast to be dropped and the track tamped. The shoulders will then be reformed. This work will provide fresh ballast for the tamper to improve the ride and help to remove wet spots that have forming on that section.

48d421_2d4eca0563f54dcdb6e7351bdf9ec58a~mv2

At County Boundary, the last part of the work is being carried out so that the line can be returned to line speed at that location. This involves the removal of 70 meters of track and the excavation of the ground below the normal ballast level. This is composed mostly of ash and the resultant spoil is being shifted to location at the former Kinlet Colliery sidings. The lower part of the excavation will then have a plastic geomesh laid and imported fresh stone material deposited to a depth of 300mm. This will be overlaid with another layer of geomesh followed by ballast to a depth of 450mm. The track will then be re-laid, ballasted and finally tamped. This work (recommended by the SVR’s consulting engineer) will ensure that we do not suffer future settlement problems as a result of the slip and subsequent remedial works. It has of course resulted in diversion of resources from some of our other planned relaying work but will hopefully negate further visits to the site to repack.

eardington

A project funded by the Friends of Eardington Station is also underway during the shutdown involving the partial rebuilding of the platform face. Although the station does not currently feature in our daily operations, a dedicated team lead looks after and maintains this wayside gem. The rebuilding of the platform will improve greatly the appearance of the station and allow consideration to its possible use on gala events at some point in the future. Some 8000 engineering bricks recovered from the London – Bristol mainline and donated by Kier Construction will be used. These have been cleaned up by the team over a period of time and will provide a genuine connection to the GWR. The rebuild is being undertaken by JSR Construction who are based less than a mile away from the station thus keeping the work local.

At Kidderminster, preparations are underway for the lining of the loco water tank similar to that carried out at both Bridgnorth and Bewdley. This work will require the draining down and drying of the tank interior followed by shot blasting. This provides a strong key to the GRP lining system that is then applied to the bottom and sides of the tank interior finishing off with a gel coat. This work is proactive maintenance of the tank and will greatly extend its life for a relatively modest cost. It is being carried out by Project Linings Ltd who have done the other tanks on the SVR to a very high standard.

The Kidderminster water column adjacent platform 1 runround is being swapped out from a fixed column to a standard GWR swing arm type similar to that on platform two side. This project has been a long time in the making having being on the cards since the 1980s. Although the current fixed column is an original Kidderminster GWR item (having been cast at Wolverhampton) the swing arm replacement will be better suited to the variety of engines the SVR sees. The replacement has been restored and new components fabricated and the original fixed column will for now be retired to the custody of Kidderminster Railway Museum for possible display.