Putting soul into our new build


The chimneys are completed and really look the part. The installation of the windows and doors has commenced and it is readily apparent that this will put some soul into the building.


The large amount of cast iron guttering required was supplied in natural finish but this has been painted up in a specially installed heated container and is ready for fitting.


The flat roof is just waiting for the weather to improve as the zinc covering requires a rising temperature above 7.5 degrees C to shape around the formers without tearing. The subcontractors are forming as much off site as possible in heated workshops to speed up the installation.


The roofing slates are due for delivery on 8th March with the main pitch roof work starting on the 12th.  We are nearing a time where the scaffolding will be dismantled to reveal the true character of the building and early indications are that it will be magnificent.

In the services room located in the adjacent listed building, all the underground ducts are in along with various cables. The exterior approach has been 75% reinstated and the only remaining task is installing a concrete floor and internal block wall which will be carried out by station volunteers.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s