New build roof

The severe snowfalls experienced before Christmas caused the best part of a week to be lost on site. The planned temporary covering over the roof was not effected and unfortunately this led to the roof trusses being exposed longer than we would have liked to the weather. The temporary roof covering will shortly be installed and allow the drying out to begin.

48d421_5b234af641284902b69b0820191d7c24~mv2

The rear flat roof of the toilets and buffet are now in a position to accept the specialist contractors to apply the zinc covering.

48d421_58990b780e7342a0b4bdf22a39d4e778~mv2

The buffet chimney stack is nearing completion to cap level in readiness for all the stone chimney caps and pots to be lifted into position with a crane.

48d421_05453b1232b14d138b43652166aace78~mv2

Inside, all of the gaps left in the interior walls for ease of movement within the building have been closed up.

The new power cable was due to be installed but has had to be postponed due to the owner of vehicle parked above the connection point disappearing on holiday.

48d421_efd97a3ddb1b41c787ab7251e6e48379~mv2

Three GWR style wall light brackets are being fabricated to be mounted on the building with appropriate style lamps.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s