WWCC Sat 27 Jan

On the weather front, it was just another dull and rainy January morning and the prospects didn’t look too bright either. Nevertheless, there were advances on several fronts.

The footbridge lamp standards got a second coat of ‘County Cream’.

IMG_6219

More rationalisation of the stores was in evidence.

The hole on the pub wall was filled with a strong mortar mix, which will hopefully solve the damp wall at the rear entrance.

IMG_6229

Under the heading of good housekeeping, the pub door onto the platform was rubbed down and painted in its first top coat.

IMG_6224

The timetable boards were black painted. The shop window frames were washed down and reputtied ready for painting next week. A strip light cover was replaced in the ladies room. The canopy lights were wiped clean.

IMG_6164

IMG_6163

Following these small but important jobs, the workshop was left in the hands of those responsible for the current reorganisation.

The tent was rearranged to allow better access for the bench refurbishment operations.

 

Advertisements

County Boundary re-ballast

At County Boundary, the last part of the work is being carried out so that the line can be returned to line speed at that location.

26906939_2014871912129701_9157857430935460072_n

27066980_2014871822129710_7917173696590628253_n

This involves the removal of 70 meters of track and the excavation of the ground below the normal ballast level.

26994354_2014871635463062_7070615644082841952_n

26991649_2014871935463032_1392426652555527765_n

This is composed mostly of ash and the resultant spoil is being shifted to location at the former Kinlet Colliery sidings.

26231829_2014871968796362_4924685579461743589_n

26907770_2014872158796343_6975853180818489215_n

27072728_2015156222101270_7826597082326305412_n

The lower part of the excavation has a plastic “geomesh” laid and imported fresh stone material deposited to a depth of 300mm.

27332492_2014872022129690_8914161385003418758_n

27072617_2015156318767927_6627834849067946583_n

This is overlaid with another layer of geomesh followed by ballast to a depth of 450mm.

27331980_2015156258767933_2847998147497213288_n

26992416_2014872112129681_8768731471313666267_n

The track is then re-laid, ballasted and finally tamped. This work (recommended by the SVR’s consulting engineer) will ensure that we do not suffer future settlement problems as a result of the slip and subsequent remedial works. It has of course resulted in diversion of resources from some of our other planned relaying work but will hopefully negate further visits to the site to repack. (pics by Leigh King, PW Dept staff)

Town footbridge temporary fix

So the temporary fix is being tried out, with the rather heavy weight positioned to hold the bridge down into place while new fixings are installed. Hopefully the bridge walkway will stay down when those weights are removed!

IMG_6203

IMG_6205

Eight holding down bolts fix the deck walkway in position and prevent it from moving excessively under live pedestrian loading. It’s believed the bolt failure has been caused by a combination of

– de-icing salts which have penetrated onto the tops of the bank supports and ‘eaten’ away at the high tensile steel bolts

– cyclic fatigue failure due to pedestrian live loading

– contraction of the main cables and lattice steelwork caused by the recent prolonged cold temperatures.

It is thought the problem has built up over a number of years but remained hidden from view due to the design detailing.

WWCC Tues 23 Jan

Another grey day, but at least we had another good turnout.  Today’s main effort, involved finally getting the three remaining footbridge handrails in place, this was successfully completed and the footbridge left open to visitors.

IMG_6211

IMG_6215

IMG_6214

The two Platform 2 extension markers were hammered into the ballast at the appropriate distance from the south end.  Elsewhere, we were made aware of a problem involving the DPM under the rear edge of the slates on the Plat 2 shelter, which was flapping in the breeze.  Approximately 12 feet of the material had to be repositioned under the edge of the slates, using ladders from the Loco Dept.

Finally, back in the shed. both footbridge lamp standards were rewired in the correct cable onto new lamp holders, the refurbished lampshades were given a coat of green paint on the outside, approximately the same colour as the original green enamel.

IMG_6221

IMG_6219

IMG_6220

WWCC Sat 20 Jan

Working with the Wailing Wall is like waiting for a bus, sometimes you wait and next to nothing happens, then like today there are so many bodies in the workshop, you have trouble getting in to unload your stuff.  Still mustn’t complain about the attendance, only the weather which started out all drizzle and fog and later developed into full scale snow storm, which fortunately later turned back to rain.

Today’s activities included security matters in the workshop, to which end we now have super secure locks fitted to both tool storage areas either end of the shed.

IMG_6141

More chocolate brown was applied to the Booking Hall doors out on to the platform.

Two new sections of point rodding were cut and drilled, to be used under the lamps from the footbridge. The lamp standards themselves were rubbed down and received a first coat of County Cream and Buildings Chocolate Brown as appropriate.

Two further sections were cut to form marker posts for the proposed extension southwards of Platform 2. these were sign written and await fixing when the weather permits.

The afore-mentioned weather precluded work to fit the footbridge handrails which are now completed and waiting in the tent.

The Railwayman’s Arms platform door outside face was given further paint-prep attention.

IMG_6153

There was a need to shore up the tent which has suffered in the strong winds, to the extent that the curtain rail at the front had become unbolted, matters were put in hand to rectify the situation and maintain security.

The cubicle door inside faces in the Ladies Room were rubbed down and given a first coat of white gloss.

The reorganisation proceeds, albeit slowly, still as hopefully the weather improves then the pace will quicken.

Winter works, small projects

More updates from the Infrastructure Manager Chris Bond

At Waterworks straight there is still a 15mph speed restriction in place imposed in June 2016, and was a contributing factor to last year’s late running and was the subject of Winter Works 2017. The area should be returning to line speed for the running season as the welding has been completed to a position that will allow this. There is some further work required but this will be done later in 2018 and consists of a final few welds and mechanical stressing on the section.

Alongside the larger scale PW projects there are some smaller but no less important works being undertaken by our volunteer gangs. This year the projects are:

  • Bridgnorth PW gang. This year there is a focus at Highley where there is a quantity of spot re-sleepering taking place within the station area. Another job being undertaken is on Highley bank where over a period of time the rails “creep” downhill and require re-setting. This involves removing keys and barring the rails back to the correct position before re-fixing. This ensure all the expansion gaps are correct.

  • Bewdley PW gang. The volunteers are having a big sort out in the carriage shed yard at Kidderminster in order to improve what is now very tired track. Considering the volume and importance of shunting moves in the yard this is essential maintenance. Joints are being dug out and sleepers replaced where necessary to improve the general state of the track. Later this year at least two of the points in the yard are to be replaced as part of upgrading this vital operational facility.