steelwork lace

The site has become rather muddy due to the heavy rain. Each day another section of the reinforcing is laced together to form more of the ground beams required and some of these have been cast. More of the timber and plywood needed for building the shuttering has been delivered in anticipation of further deliveries of concrete. This work will carry on until all the ground beams are completed and preparation will then be made to create the building slab that will sit on top.
http://www.svrlive.com/bridgnorth-development